The Metro line between South Shields and Chichester is to close for five weeks as part of the £21m development of the town’s new bus and Metro interchange.

Nexus, the public body which owns and manages the Tyne and Wear Metro, has to carry out track and signalling upgrades so that Metro trains can serve the new interchange when it opens in 2019.

The major line closure will start from Monday 1 October and will run until Saturday 3 November. When the line is closed a frequent replacement bus service, 900, will be provided. Metro services will continue to operate as usual from Chichester towards Newcastle and Sunderland.

From Sunday 4 November Metro trains will be unable to call at platform 2 at Chichester until the interchange works are completed in August 2019.  Further information about this can be found at www.nexus.org.uk/metro/modernisatio

Managing Director of Nexus, Tobyn Hughes, said: “The £21m new transport interchange is a really exciting development for South Shields. We are now at a key stage where we need to get the Metro tracks and signals set up so that our trains can stop at the new interchange when it opens in 2019.

“We have to close the line between South Shields and Chichester for four weeks from 1 October so that the work can be done safely and effectively. We will also have to close platform two at Chichester Metro station until August 2019.

“I’m sorry for any inconvenience this will cause to our customers in South Tyneside. The long term benefit will be a brighter, better and more modern transport hub in South Shields, which we think will attract more people into the town for shopping and leisure.”

South Tyneside Council is working with partners Muse Developments and Nexus, and construction contractor Bowmer and Kirkland, to deliver the new South Shields interchange on Fowler Street and Keppel Street.

Construction of the interchange, which forms Phase Two of the £100m South Shields 365 regeneration masterplan, began in April.

It will provide South Shields with a landmark new building housing both the Metro and bus concourses under one roof.

Planning permission was granted last year for the transport interchange, as well as outline planning permission for Phase three, new retail and leisure development.

The project received £9.4m from the Local Growth Deal through the North East Local Enterprise Partnership. The Local Growth Deal is supporting major capital investments to promote innovation, economic and skills infrastructure and sustainable transport across the North East LEP area.

Further information about the planned closure of Platform 2 at Chichester Metro station:

Although the line between Chichester and South Shields will re-open on Sunday 4 November, trains will be unable to call at platform 2 at Chichester until the interchange works are completed in August 2019.  This is because of signalling constraints in place to allow building work to take place.  As a result trains leaving South Shields towards Newcastle will not call at Chichester from Sunday 4 November 2018 until August 2019.

Platform 1 at Chichester will remain open throughout the interchange construction works.

Passengers wishing to travel from Chichester in the direction of Newcastle are advised to board a train from platform 1 at Chichester to South Shields and remain on the train when it terminates, as it will then travel back towards Newcastle.

Passengers wishing to travel from South Shields to Chichester are advised to remain on the train until Tyne Dock, change to platform 1 and return to Chichester platform 1.